Energy and Cost Analysis

Ünlü Engineering presents different alternatives to their customers to keep the balance between first investment and operational cost.
Ünlü Engineering can simulate the designed buildings with licensed software. Addition to standard heat calculations all mechanical systems that will be used in the building can also be selected by software. Consequently all equipments are selected with correct diversity ratio. This prevents overdesign and minimizes first investment costs.

Photo 1: Sample Schematic System

According to simulation reports, detailed energy analysis is obtained. Energy consumption values and costs are also defined with these reports. Furthermore lifecycle costs can also be calculated for the system alternatives.

COMPONENT

ANNUAL COST
(TL)

(TL/M²)

PERCENT OF TOTAL
(%)

Air System Fans

23.034

9,086

9,3

Cooling

22.562

8,900

9,1

Heating

44.558

17,577

18,0

Pumps

5.376

2,121

2,2

Cooling Tower Fans

9.535

3,761

3,9

HVAC Sub-Total

105.065

41,446

42,5

Lights

84.236

33,229

34,1

Electric Equipment

57.876

22,831

23,4

Misc. Electric

0

0,000

0,0

Misc. Fuel Use

0

0,000

0,0

Non-HVAC Sub-Total

142.112

56,060

57,5

Grand Total

247.177

97,506

100,0


Table 1: Operational Costes of a Simulated Office Building



Photo 2: Operational Costes of a Simulated Office Building Percentages